MRD- Subprojects implementation

(October 2013)
CONTRACT No.CONTRACT DATAREMARKS

MRD-CW1
Stage2
Prey Veng

Contract Value: $1,260,437.64
Final Contract:  $997,637.02
Completion date: 23 Dec 2012
Actual Completion: 21 Dec 2012
End of Defects Liability:21 Jun 13
  • Defects Liability Certificate was issued.

MRD-CW2
Stage2
Kampong Cham

Contract Value: $2,094,309.21
Final Contract:  $1,825,950.86
Completion date: 23 Dec 2012
Actual Completion: 23 Dec 2012
End of Defects Liability:23 Jun 13
  • Due to overloading, KC1 was seriously damaged.
  • Defects Liability Certificate was issued.

MRD-CW3
Stage 2
Siem Reap

Contract Value: $1,297,196.78
Final Contract:  $1,061,470.35
Completion date: 23 Dec 2012
Actual Completion: 21 Dec 2012
End of Defects Liability:21 Jun 13
  • Defects Liability Certificate was issued.

MRD-CW4
Stage 2
Banteay Meanchey

Contract Value: $2,041,088.89
Final Contract:  $1,947,233.55
Start date:   16 July 2012
Completion date: 16 Jan 2013
Actual Completion: 20 Mar 2013
Defects Liability: 6 months
  • Time extension was provided as a result of 2012 flooding.
  • Defects Liability Certificate is schedule to issue on 20 September 2013 after final inspection.

MRD-CW8
Stage 2
Kampong Thom

Contract Value: $648,259.88
Final Contract:  $588,885.31
Completion date: 23 Dec 2012
Actual Completion: 21 Dec 2012
End of Defects Liability:21 Jun 13
  • Defects Liability Certificate was issued.

MRD-CW5-Lot1
Stage 3
Prey Veng

Contract Value: $1,349,667.97
Start date: 02 July 2013
Completion date: 02 Jan 2015
Defects Liability: 365 days

  •  Not much progress as rain already started
  • Due to budget constraint, contingency was removed through contract variation No.1

MRD-CW5-Lot2
Stage 3
Kampong Cham

Contract Value: $1,921,755.89
Start date: 02 July 2013
Completion date: 02 Jan 2015
Defects Liability: 365 days
  • Not much progress as rain already started
  • Due to budget constraint, contingency was removed through contract variation No.1

MRD-CW6-Lot1
Stage 3
Kampong Thom

Contract Value: $1,659,607.16
Start date: 02 July 2013
Completion date: 02 Jan 2015
Defects Liability: 365 days
  • Not much progress as rain already started
  • Due to budget constraint, contingency was removed through contract variation No.1

MRD-CW6-Lot2
Stage 3
Siem Reap

Contract Value: $1,299,162.73
Start date: 02 July 2013
Completion date: 02 Jan 2015
Defects Liability: 365 days
  • Not much progress as rain already started
  • Due to budget constraint, contingency was removed through contract variation No.1

MRD-CW7
Stage 3
Banteay Meanchey

IFB was advertised on 20 September 2013