MPWT – Subprojects implementation

(October 2013)
CONTRACT No.CONTRACT DATAREMARKS

MPWT-CW1
Stage 2
Prey Veng

Contract Value:$3,383,059.32
Variation 1:$328,783.95
Start date: 22 May 2012
Completion date: 22 Jan 2013
Time Extension1: 22 Mar 2013
Time Extension2: 31 Jul 2013
  • NOL on contract variation No. 1 was received from ADB on 21 June.
  • No particular issue was found
  • The completion certificate was already issued.

MPWT-CW2
Stage 2
Prey Veng

Contract Value:$1,992,174.25
Start date: June 2012
Completion date: 18 Mar 2013
Time Extension: No
  • Completion Certificate issue in March.

 

MPWT-CW3
Stage 2
Kampong Cham

Contract Value:$1,328,276.54
Start date: June 2012
Completion date:18 Mar 2013
Time Extension: No
  • Completion Certificate issue in March.

 

MPWT-CW4
Stage 3
Prey Veng

Contract Value:$806,898.27
Start date: 19 Dec 2012
Completion date:31 Oct 2013
Time Extension: Not required
  • Completion Certificate was already issued in September 2013.
  • No issue was found.

MPWT-CW5
Stage 3
Prey Veng

Contract Value: $1,325,663.24
Start date:11 Jan 2013
Completion date:11 Nov 2013
Time Extension: not required yet
  • Significant progress was achieved for the last few months, expect to be completed on time.
  • Recommended to complete detour roads before the rainy season in order to maintain traffics.

MPWT-CW6a
Stage 3
Kampong Cham

Contract Value:$1,268,752.17
Variation: Not yet known
Start date: 19 Dec 2012
Completion date:03 Dec 2013
Time Extension: not required yet
  • The progress is far behind the schedule, only 13.5% Against 66.9%. The slow progress was mainly due to selection of subgrade materials as the contractor is reluctant to transport from long distance.
  • The submitted revised schedule is 4 months behind the contract schedule.

MPWT-CW6b
Stage 3
Kampong Cham

Contract Value:$ 2,927,997.55
Variation: Not yet known
Start date:29 Apr 2013
Completion date:17 Feb 2014
Time Extension: not required yet
  • The contract just started with the progress of 6%.

MPWT-CW6c
Stage 3
Kampong Cham

Contract Value:$1,522,735.70
Variation: Not yet known
Start date:29 Apr 2013
Completion date:05 Feb 2014
Time Extension: not required yet
  • The front slab of box culvert at PK 9+478 coincides with the existing fence of local villager. The box culvert is being redesigned to avoid such impact.
  • The progress was accelerated for the bridge works.

MPWT-CW8
Stage 3
BAT and BMC

NOL from ADB
  • BER was already submitted to ADB for Prior Review

MPWT-CW7
Kampong Cham

Under Preparation
  • The IFB was advertised on 14 September 2013 and the bid opening will be on 16 October 2013