MoWRAM- Subprojects implementation

(October 2013)
CONTRACT No.CONTRACT DATAREMARKS

MoWRAM-CW1
Stage 2
Prey Veng

Contract Value: $1,140,859.39 ($230,842.37 for Lam Loang +$910,017.02 for Toul Skea)Start date: June 2012
Completion date: 25 Dec 2012
Time Extension1: 30 Mar 2013
Time Extension2: 31 Jul 2013
  • The progress is extremely slow.
  • The completion certificate was already issued.

MoWRAM-CW2
Stage 2
Prey Veng

Contract Value:$1,188,483.46
Start date: 16 July 2012
Completion date: 16 Jan 2013
Time Extension: 31 Mar 2013
  • Completion Certificate was already issued.
  • Progress and Retension payments still pending (submitted on 08 May 2013)

MoWRAM-CW3
Stage 3
Prey Veng

Contract Value:$ 521,873.83
Contract Date: 30 July 2013

  • PRC approved BER on 07 June 2013
  • The start date was delayed till December due to assess road and wet materials.

MoWRAM-CW4
Stage 3
Kampong Cham

Under Bid Evaluation
  • The start date was delayed till December due to assess road and wet materials.

MoWRAM-CW5
Stage 3
Kampong Cham

Contract Value:$754,754.58
Start date:21 May 2013
Completion date:16 Nov 2013
  • The start date was delayed till December due to assess road and wet materials.

MoWRAM-CW6
Stage 3
Siem Reap

Invitation for Bids was already advertised

MoWRAM-CW7

Cancelled

MoWRAM-CW8

Cancelled

MoWRAM-CW9
Stage 2
Kampong Cham

Contract Value:$ 318,842.81
Start date: 16 July 2012
Completion date:16 Nov 2012
Time Extension: No
  • Completion Certificate was already issued. No issue was found.

MoWRAM-CW10/11
Stage 2
Battambang

Contract Value:$ 898,489.89
Start date: 16 July 2012
Completion date:16 Feb 2013
Time Extension: 31 Jun 2013
  • Minor defects are being fixed before issuing the completion certificate.

MoWRAM-CW12
Stage 2
Kampong Thom

Contract Value: $877,937.49
Start date:16 July 2013
Completion date:16 Jan 2013
Time Extension: 31 May 2013
  • Completion Certificate was already issued. No issue was found.

 

MoWRAM-CW13
Stage 3
Kampong Thom

Contract Value: $686,982.25
Contract Date: 30 July 2013
  • The start date was delayed till December due to assess road and wet materials.

MoWRAM-CW14

Cancelled

MoWRAM-CW15a-b

Failed bid           Under consideration for rebid

MoWRAM-CW15c

Awarded
  •  Construction is under progress